Volunteers Stadium Report Week One
Saturday, 28th May 2016It was good to see some old faces from last season in to help during the week
Progress in Week One
First main entrance stairs scrubbed down painted and ready for the new season.
Prep work on main stand railing fully de-rusted and first coat primer
applied.
Home end main stand final paint coat applied.
It was good to see some old faces from last season in to help during the week they enjoyed themselves with the banter.
Warning due to circumstances work for next week will only take place on Tuesday 31 May but normal days of Tuesday Wednesday Thursday will continue the following week.
Contact Dave Blackburn E mail chippyblackie@yahoo.co.uk tel
07506200846
Views : 4,815